Under RCRA, a generator must obtain a permit to store waste over 90 days.

Study for the PE Environmental Qualitative Exam. Practice with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Multiple Choice

Under RCRA, a generator must obtain a permit to store waste over 90 days.

Explanation:
Hazardous waste generators are allowed to accumulate waste on-site for a limited time without a permit. That accumulation window is 90 days for most generators (with longer limits, such as 180 days, for certain smaller generators under specific conditions). If a generator needs to store waste beyond that allowed period, the storage activity is no longer just generator accumulation and generally must be conducted under a permitted storage facility or by transferring the waste off-site. So, storing waste for more than the permitted accumulation period typically requires a permit to do so.

Hazardous waste generators are allowed to accumulate waste on-site for a limited time without a permit. That accumulation window is 90 days for most generators (with longer limits, such as 180 days, for certain smaller generators under specific conditions). If a generator needs to store waste beyond that allowed period, the storage activity is no longer just generator accumulation and generally must be conducted under a permitted storage facility or by transferring the waste off-site. So, storing waste for more than the permitted accumulation period typically requires a permit to do so.

Subscribe

Get the latest from Examzify